Skip to content

The close, compressed

Currency

Every finance team knows its close date. Fewer can say which task sets it. Month-end is a chain of dependencies — bank before receivables, receivables before intercompany, intercompany before consolidation — and the books close when the longest chain finishes, not when the busiest team does.

So automation only buys days where it touches that chain. Rules and integrations take out the mechanical hours; AI moves matching and accruals into the month, before the close window opens, and drafts the commentary for FP&A to edit. Switch it on task by task and watch where the date is decided — until the only thing left setting it is the review a person has to sign.

Three cases

6

Across Europe, the UK and the Americas. Intercompany, consolidation and eliminations grow with the group; a single entity has none.

Close lands

WD7

working day, by hand

Effort removed

0 h

of 148 person-hours a month

Critical path

9 tasks

end to end, with no slack

Constraint now

Intercompany matching

Group reporting · 9 h

Verdict

Run by hand, the close lands on working day 7.

The constraint now is intercompany matching, the longest step still done by hand on a nine-task critical path. Automating it next brings the close to working day 6.

Close calendar · 6 entities

Switch a task to automate it
  • Critical path
  • Has slack
  • Automated
  • By hand

Task by task

Hours are elapsed · 8-hour working days from 09:00
Close schedule task by task: elapsed hours by hand and now, window and slack.
TaskHoursEnds
Bank reconciliationTreasury8 hWD1 17:00Critical
Receivables & revenueReceivables7 hWD2 16:00Critical
Payables cut-offPayables9 hWD2 10:006 h slack
AccrualsGeneral ledger6 hWD2 16:0012 h slack
Payroll journalsPayroll4 hWD1 13:0023 h slack
Fixed assets & prepaymentsGeneral ledger4 hWD2 14:0014 h slack
Intercompany matchingGroup reporting9 hWD3 17:00Critical
FX revaluationGeneral ledger3 hWD4 12:00Critical
ConsolidationGroup reporting6 hWD5 10:00Critical
EliminationsGroup reporting4 hWD5 14:00Critical
Tax provisionTax6 hWD5 10:007 h slack
Flash P&LFP&A3 hWD5 17:00Critical
Management packFP&A8 hWD6 17:00Critical
Review & sign-offController & CFO6 hWD7 15:00Critical
Person-hours148 hAll by hand

Notes on the model

What it shows

  • Automation off the critical path saves effort, not days. The two headline numbers move independently, and most business cases only quote the first.
  • The constraint migrates: intercompany matching first, then the management pack, and finally review and sign-off — the floor no tool removes.
  • Group structure matters as much as tooling. Add entities and intercompany, consolidation and eliminations stretch faster than anything else.

How it works

  • Fourteen tasks, each with an owner, an elapsed time, a crew and its dependencies. A forward pass gives earliest start and finish, a backward pass gives slack, and the constraint is the longest step on the critical path still done by hand.
  • Each lever shortens its task. Where it lets the work run in-month — accruals, schedules, intercompany — it also removes the wait on cut-off.
  • Effort is elapsed time multiplied by crew. The annual value prices the hours removed at an illustrative fully loaded hourly rate.
  • Entity-level work runs in parallel, so elapsed time creeps up with group size while person-hours grow almost linearly. Group-level work grows with the web of intercompany flows.

What it leaves out

  • Durations are illustrative, calibrated for a six-entity group on 8-hour working days. Your own close calendar is the only input that matters.
  • Queueing, people juggling several tasks, late adjustments from the business and audit requests are all left out.
  • Levers are on or off. In practice each one ramps, and each needs controls strong enough to trust its output before the review can shrink.